According to Core Clause 50.2 of NEC3 and 50.3 of NEC4, the amount due to the Contractor is the total of:
Price for Work Done to Date; plus
other amounts to be paid to the Contractor (such as compensation events); less
any amounts to be paid or retained from the Contractor.
The definition of...