Cases - British Westinghouse Company v Underground Electric Railways
Record details
- Name
- British Westinghouse Company v Underground Electric Railways
- Date
- [1912]
- Citation
- AC 673
- Keywords
- Construction – litigation – loss and expense – mitigation – measure of damages – steps required in mitigation of loss – steps which a reasonable and prudent person would ordinarily take in the course of his or her business
- Summary
-
This case confirms the general mitigation principle that a claimant must take all reasonable steps to minimise the loss to him or herself as a result of the breach, but that the claimant is under no obligation to take any step which a reasonable and prudent person would not ordinarily take in the course of his or her business.